Client case

Space savings

The client in this study is a leading global provider for a new world of communications. With a leadership position in emerging markets, the company leverages its advanced solutions capabilities and domain expertise across its global networks to deliver managed solutions to multi-national enterprises and service provider consumers. With forty-two data centers globally and more than one million sq. ft. of net area, they offer services in major international locations around the globe.

Projectinformation

UPS type: Dynamic UPS
Power module: 1,670
No-break rating: 1,336 [email protected] 0.8 PF of net usable power
Engine rating: Standby rated at 1,670 kVa
Phase 1 install: 4 modules
Total install: 14 modules in total
Operating voltage: 400V / 50Hz
Configuration: 2N, Isolated Parallel
Housing: Outdoor weatherproof containers

Downloads

Stadium

Project Challenge

When our client decided to construct a new data center in Singapore, minimizing the facility’s Gross Floor Area (GFA) and maximizing the space available for revenue-producing server racks was extremely important. Within these competing ideals the company still needed sufficient space to accommodate the necessary critical components such as the UPS system. As long as data centers have been constructed, organizations have worked hard to minimize the amount of space dedicated to supporting infrastructure, and

maximize the amount of revenue-generating rack space. This is often a difficult equation to balance, and this client site was no different.

To solve this problem, the client needed to find not only the most appropriate UPS technology, but also a company with the engineering knowledge and installation experience to help them configure the highest density of UPS power in the least amount of space. After considering several options, they selected HITEC.

Project Solution

HITEC helped this particular client preserve GFA with an innovative solution: choosing containerized Dynamic UPS systems and stacking them on the data center’s rooftop. When it came to expanding the data center in the future, HITEC was asked if it would be possible to reconfigure the existing UPS system when adding new units to support the increased building load. To answer this question, HITEC proposed an isolated parallel configuration that reduced the number of redundant units within the overall system and increased the system reliability. This approach also allowed for an improvement in the operational efficiency of

both the Dynamic UPS system and the building as a whole. At full build, the facility will be supported by a total of 14 Hitec UPS units on the roof of the building. Each containerized Dynamic UPS module weighs in at 110,000 pounds. The rooftop deployment of 14 of these units required careful planning. HITEC engineered a solution for stacking the units two at a time in such a way that would ensure complete continuity to the building throughout the installation process, as well as for future expansion.

Client cases

受到500多家客户的信任

通过了解您的市场,HITEC始终为每个特定项目提供最佳解决方案。

Browse all cases

Case

Safety of air traffic

Case

No-break power for mechanical loads in pharmaceuticals

Case

No-break power for mechanical loads in manufacturing

Case

Powering a safe journey

Case

Continuous supply to mechanical loads for a pharmaceutical production line